A different perspective on the current state of Jeffco schools

Category: Jeffco Capital Improvement Program (Page 2 of 2)

Winners and Losers with Jeffco’s FF&E Bond Projects

Something very strange is happening with the FF&E projects in Jeffco’s Bond program.

In December, there were 63 listed FF&E projects on the CAAC report. 12, or nearly 20%, with costs of $3.2M, had no Original Budget, meaning they were originally unplanned and out-of-scope. If you look through the CAAC notes you will see that there has never been a discussion related to these project additions. This is not the “monitoring” that Jeffco taxpayers were promised when the District was campaigning for bond approval. These are the “winner” schools.

Yet, they aren’t the only “winner” schools. There are an additional 11 schools with current costs more than $200,000 over their original estimated budget. Variances for these projects range from 81% over budget to 1950% over budget (that number is not a typo). Is this just a result of bad estimating or are these schools getting more than they were originally scheduled to get? Who approved these additions and overages?

Jeffco FF&E Projects more than $200,00 over budget

It would be one thing if the vast majority of “estimating” errors were all in the same direction, but unfortunately that’s not the case. There are 14 schools with Current Estimates more than $200,000 less than the Original Estimate. Cost variances for these schools range from 25% to 80% less than the original. This far exceeds what anyone could reasonably expect to see from good purchasing practices. These underages are representative of schools not getting what they were originally scheduled to get. These are the “loser” schools. Once again, what is the process for determining and approving these shortfalls?

Jeffco FF&E Projects more than $200,000 under budget

As you can see from this spreadsheet, extracted from the December CAAC notes, something is not right regarding FF&E projects. The degree of variance is truly incomprehensible. Are there “winners” and “losers” or is this an indicator of an unbelievable level of incompetence? Either way, this is not right and shouldn’t be tolerated.

Taxpayers were promised accountability and transparency. Unfortunately, because these projects can be “broken” up to be under $500,000, they never show up before the Board. But, someone knows what is happening here and the winner and loser schools, along with taxpayers, deserve to know what is going on.

Jeffco’s Damning Moss Adams Bond Review

Last week Jeffco citizens heard the Moss Adams presentation relating to their review of the Capital Improvement Program.

If you looked at Jeffco’s Next Steps slide, you would think that only a few simple communications tweaks were needed.

This was reinforced by Superintendent Dorland telling the Board that “Most projects are at or near budget”.

However, if you read the full report, this couldn’t be farther from the truth.

First, it is completely false that most district projects are at or near budget.

The Moss Adams report shows that 59% of In-progress projects are over budget, with 19% of all projects expected to exceed their budget by over $500,000.

It is worse for Completed projects where 67.8% are over budget, with 18.8% exceeding their budget by more than $500,000.

Dorland was wrong. If someone gave her that faulty information they should be fired. If she said that without doing the proper research, then she should be reprimanded. She should always give the Board accurate information.

Regarding the report, the findings and recommendations were much more serious than Jeffco staff wants people to believe.

Here are the highlights:

  • The current program cost estimate is now $136M more that what was initially shown to voters in 2018.
  • Bid tabulations or evaluations for the selection and award of projects were not available.
  • The District does not have policies and procedures specific to the change order process (i.e., review process, thresholds, approval process, approval levels, etc.).

These are egregious. Jeffco is talking about nearly 25% cost overruns (above the included 10% project contingency), with Reed telling the Board to expect another $43M in overages before the program is over.

Not having project selection evaluations means that the program is not transparent and is ripe for favoritism and or kick backs.

The same can be said regarding the change order process. This leaves the program ripe for vendor overcharging or kick backs.

None of these are good, but all were glossed over in the report review session.

To make matters worse, instead of acknowledging and addressing the Moss Adams findings and recommendations, all Director Rupert did was fault the consultants, make excuses and praise staff for the program.

It was appalling.

In addition, Rupert made a point that the program was not based on the 2016 Facilities Master Plan, when former CFO Kathleen Askelson, in her January 2021 bond review report stated that it was.

Rupert was wrong and Dorland was wrong.

The report was more damning than anyone wants to admit.

We can only hope that Dorland can clean the mess up, but her statements and actions to date don’t give me much hope.

Jeffco Schools is lying about school bond projects being under budget

Jeffco’s Flipbook (and here if Jeffco deletes or changes it) is declaring multiple schools are under their bond program budget when they clearly aren’t.

I will document two of the schools here, Fremont ES and Belmar, but there are many more, including Arvada K-8, Columbine Hills, West Jeff MS, Welchester, Eiber and Semper.

Why is this happening? There are only two answers, either complete incompetence on the part of staff or a desire to mislead the public into believing the management of the program is not as bad as it really is.

Belmar – tagged with a green arrow in the Flipbook

The Flipbook states that Belmar has a budget of $1,068,000.

The current CAAC report shows Belmar costs as:

Efficiency & Future + Paving $848,999
Hazmat Costs $85,281
FF&E $382,202
Total $1,316,482

This is nearly $250,000 over budget and does not include additional costs such as security glass, site lighting, IT cameras and network upgrades.

Fremont ES

The Flipbook states that Fremont has a budget of $1,289,000.

The current CAAC report shows Fremont costs as:

Efficiency & Future Ready $1,087,700
FF&E Costs $334,083
Hazmat Costs $102,186
Total $1,523,969

or more than $230,000 over budget, not including additional costs such as security glass, site lighting, IT cameras and network upgrades.

Jeffco is lying to the public to present a picture that they are good managers and stewards of our money, when the exact opposite is true. This is not a good look.

Jeffco should fix this immediately. In addition, Jeffco should show the total costs for each school project so that voters and taxpayers can see the truth.

You Can’t Trust Jeffco Schools Capital Asset Advisory Committee (CAAC)

Jeffco Schools Capital Asset Advisory Cmte can’t be trusted to make good financial decisions and gets played as fools by Tim Reed and Steve Bell. They are utter failures at being good stewards of Jeffco’s taxpayers’ money.

They are responsible for overseeing now $110M in cost estimate overages of the Capital Improvement Program and recently agreed to spend an additional $17M for a new gold-plated swimming pool for the community of Arvada.

The $17M and decision process for a new Arvada community pool is egregious. Here’s why:

1. Jeffco swim teams will use the pool approximately 10% of the time, Arvada residents the rest. Yet Jeffco will pay for 50% of the $33M-$35M construction costs. That doesn’t seem equitable. Not one CAAC member questioned that arrangement or suggested that Jeffco’s share be reduced to something reasonable like $7M.

2. Reed told the CAAC that construction costs for a Jeffco owned 50 meter pool would be $15M-$20M. Not one CAAC member asked if Arvada was taking advantage of Jeffco by building a gold plated facility that would cost $15M more than Reed’s estimate.

3. No one asked what was even included in that additional $15M.

4. Other area rec center pools in Wheat Ridge and Evergreen are 25yd pools. No one asked why the Arvada facility had to be a 50 meter pool. No one asked what a 25 yard facility would cost.

5. No one asked what the cost would be to add 25 yard pools at High Schools. Smaller pools, locker rooms already in place and possibly shared walls would result in lower costs.

6. Not one CAAC member asked what the implications and precedent would be set for the other 4 Rec Districts in Jeffco when their pools “age out”. Would Jeffco help those Rec Districts fund their new pools in the future? Or, would Arvada residents be “winners”? In 2018 Evergreen voters rejected a bond package that included pool upgrades to their 50 year old failing facility.

7. No one asked about the equity. No one asked why Reed and Bell thought it was fair for Lakewood or Evergreen residents to pay for an Arvada community pool.

7. Not one CAAC member asked what Jeffco schools facility needs would not get accomplished because $17M went into Arvada’s new pool. Taxpayers were told that Jeffco had $1.3B in facilities needs when they were asked to approve the $567M bond. Are those not real needs now? Shouldn’t there be a prioritized list of projects awaiting funding that this project is compared against? Replacement schools for example? Isn’t prioritization a key function of the CAAC? Yet, trade-offs weren’t even discussed.

8. Not one CAAC member asked about the certainty of Arvada voters passing a bond to fund the facility. A recent bond to fund upgrades in Evergreen Rec district, including pool upgrades failed.

9. Not one CAAC member questioned Reed when he said that the pool would be funded from Capital Transfer, like Cap Xfer is some unlimited source of funds. Jeffco Schools promised voters that Capital Xfer would be committed to the CIP for 6 years. There is no additonal money. In fact, Jeffco is already shortchanging the CIP by $12M

10. Not one CAAC member asked how funding Arvada’s pool would affect voter sentiment District wide when Jeffco needs another capital bond passed in a few years. The current bond was carefully crafted so that everyone got something and still just barely passed. If Jeffco schools pays for Arvada’s gold plated facility, you can be guaranteed it will not sit well with Lakewood, Wheat Ridge and Evergreen voters in the future.

In a 6-0 (one absent) vote, the CAAC recommended to endorse the project.

The committee’s failure to ask reasonable questions relating to spending $17M on a pool facility for a specific community is indicative of the overall lax oversight and general negligence in the CAAC’s role as stewards of Jeffco taxpayers’ money.

Jeffco’s CAAC can’t be trusted to make good financial decisions.

Jeffco taxpayers deserve better!

Jeffco Officials Were Deceptive and Not Completely Honest Regarding Jeffco’s Capital Improvement Program

Recently, Colorado Community Media, including Jeffco Transcript and Arvada Free Press printed an article by writer Bob Wooley about Jeffco’s Capital Improvement Program.

For the most part, Wooley did a good job of attempting to explain a financially complex program. However, there were some comments and statements made by Jefferson Public Schools’ officials that were misleading or downright false.

I’ve outlined several of those areas below:

1. The article states:

After the Bond passed, the project’s estimated costs were increased by nearly $32 million for a revised total of just under $737 million for the program.

TRUE – $32M in hidden costs were added to the program

After the bond passed, $32M in costs were added to the flipbook for the same list of projects. The use of $32M in contingency to cover these costs was essentially hidden.

2. The article states:

District officials say the increase was a result of changes in scope, market conditions, incorrect estimates or various other factors like asbestos removal, which were determined once the District was able to perform more in-depth evaluations of each individual project.

PARTIALLY TRUE – 81 schools’ cost estimates increased by EXACTLY 5%

While I agree that factors such as scope changes, market conditions and incorrect estimates can result in changed estimates, that doesn’t fully explain the extent of the cost estimate changes between the first and second flipbooks. The project costs for 81 schools, or nearly 60% of the total, increased by EXACTLY 5%. This is not indicative of changes in scope or incorrect estimates. That’s indicative of using Excel to pad costs.

3. The article states:

We told voters we would accumulate six years of approximately $20 million at the back-end to fill up the program,” Reed says.

FALSE – Voters were told $23M

Voters were told that exactly $23M annually in Capital Transfer would be accumulated. In reality only $20.9M annually is currently being transferred. That means there is a $12.6M shortfall in stated revenue, again made up with Contingency.

4. The article states:

and over $3.5 million was spent on hazmat expenses (which technically, do not count as overages).

FALSE – Hazmat costs ARE overages

  1. Why aren’t $3.5M in hazmat expenses considered overages? Any decent construction project manager with 50 year old buildings knows there is asbestos in those buildings that will have to be mitigated. Mitigation costs should have been factored into the original estimates.
  2. Where is the money coming from to pay for the hazmat expenses? It’s coming from the District’s program contingency. Therefore, technically, and for all intents and purposes, hazmat expenses are program costs that reduce available contingency This is merely an attempt by Reed to put lipstick on a pig to make $3.5M in overages not seem like the $3.5M in overages hazmat costs really are.

5. The article states:

In a document Reed says is now posted to the Capital Asset Advisory Committee (CAAC) website, all budget variances are listed with specific overage amounts and the reason for the cost variance.

FALSE – This document lists variances against revised cost estimates, not original estimates

This document hides $32M in cost increases. That’s deception.

6. The article states:

Therefore, the precise amount of contingency that’s been spent on actual projects thus far is $65,815,424.

FALSE – The amount of contingency allocated is currently over $110M

$65M from what Reed wants people to believe is the contingency spent, plus $3.5M in hazmat, plus $32M in increased estimates plus $9M from recent fields project = $110M in contingency allocated.

7. The article states:

I’m not a construction guy,” Bell said. “But we have a construction guy and I was speaking to him this morning and he said “you know, a year ago the cost of steel was $53 a ton — today it’s $79.” A year ago did anybody know it was going to go from $53 to $79? No.”

MISLEADING – Cost of steel is only one small component of cost increases

Both Tim and Steve have told the Board on several occasions that they have been getting good pricing due to the pandemic. And, this report shows that non-residential construction costs have been relatively flat in Denver for the last 2 years, increasing by only 2.1% total over that time. In addition, there are numerous projects that had no steel involved that are significantly over budget. This is a misleading and deceptive statement.

8. The article states:

According to Tim Reed, Jeffco’s Executive Director Facilities & Construction, the amount of contingency that had been spent as of Feb. 22, was just over $81 million, of which nearly $12 million went to charter schools…”

MISLEADING to FALSE – $12M to Charters came from Bond Premium

The agreement with District Charters was that Jeffco would share approximately 10% of all bond proceeds with Charter schools. The $12M Tim Reed is referring to is based on Charters’ share of accrued interest and bond premium. This has nothing to do with District contingency.

The bottom line is that the Capital Improvement Program has already spent or allocated $24M over its original $86M contingency budget ($110M total) only 2.5 years into the program. In addition, Jeffco has hidden a $12M revenue shortfall from Capital Transfer. The amount of deception and lack of accountability for large cost increases is truly unbelievable.

Newer posts »